NEWMeta Commits to 1 GW Custom AI Chip Capacity For 2027 Rollout
topics ๐Ÿค– AI๐Ÿ’ป Tech tags AIAI InfraAI Chips keywords NvidiaBroadcomTSMC

The MTIA 450 chip, code-named Arke, will begin deployment across Meta data centers in the first half of 2027 to lower the energy and financial cost of running AI models. A second next-generation chip, the MTIA 500 code-named Astrid, will enter data centers by the end of 2027. Meta has committed to more than 1 gigawatt of custom silicon capacity over a 12 month period to provide better performance per watt than current Nvidia systems.

Meta partnered with Broadcom for design and TSMC for manufacturing, receiving the first 12 Arke units on Sept. 1 with testing results within 2% to 3% of simulations. The company canceled a separate chip project called Olympus after determining that a design for both training and inference would cost 30% more. Later generations of custom silicon will focus on fiber optic technologies to increase throughput and speed.

See all 6 tweets โ†’